RAILWAY PROTECTION ZONE (RPZ)

Railway Protection Zone (RPZ) is defined as a zone designated area by the Director General, Agensi Pengangkutan Awam Darat (APAD) in which the railway structure is located, whereby activities that may pose danger to the railway structure are subjected to regulations/restrictions. These Regulations may be cited as the Railways (Railway Protection Zone) Regulations 1998. This area is protected from any development unless with permission from the Authority. RPZ is a part of the initiatives by the Authority to ensure safe and reliable operation of MRT.

 

DEVELOPMENT BUILDING CONTROL

Development Building Control (DBC) is in-charge to safeguard the MRT Structures in the MRT Railway Protection Zone (RPZ) as per the Railways (Railway Protection Zone) Regulations 1998. DBC, MRT Corp role is to ensure all engagement with Third parties / Stakeholder are as per Standard Operating Procedure and Railway Protection Zone 1998 (RPZ) regulation requirements.

Developments within the MRT Railway Protection Zones must conform to the Railways (Railway Protection Zone) Regulations 1998 (RPZ 1998) which includes: –

  1. Comply to technical specifications in RPZ 1998.
  2. Obtain ‘No Objection’ letter from MRT Corp.
  3. Obtain Letter of Approval from Agensi Pengangkutan Awam Darat (APAD).

All works that to be constructed within the MRT Railway Reserves Zone cannot commence without the No Objection Letter from MRT Corp and Approval Letter from APAD.

Restricted activities within MRT RPZ are briefly listed below: –

  • New Developments
  • Any works breaching by third parties in the reserves
  • New Pedestrian Link way connecting to MRT Stations
  • New Entrance Road/Underpass connecting to New Developments
  • Utilities upgrading and maintenance works
  • Excavation, earthwork & backfilling
  • Storage of material
  • Use of crane, drilling machine, pile rig, excavator or any heavy equipment
  • Landscape works & trees
View Klang Valley Rail
Transit Map
SSP Line
Project Updates
Interested in doing
business with us?

APPLICATION FLOW FOR WORKS WITHIN MRT RAILWAY PROTECTION ZONE (RPZ)

REFERENCE DOCUMENTS FOR WORKS WITHIN MRT RAILWAY PROTECTION ZONE

RAILWAYS (RAILWAY PROTECTION ZONE) REGULATIONS 1998
Railways (Railway Protection Zone) Regulations 1998 was initially under Railway Act 1991 Railway Act 1991 was superseded by Land Public Transport (Amendment) Act 2018.

MRT RAILWAY PROTECTION ZONE SUBMISSION LIST
This submission list is to guide the applicants to prepare and submits the related documents to Development Building Control (DBC) Section, MRT Corp.

INSTRUMENTATION & MONITORING (I&M) GUIDELINES
This guideline outlines the minimum requirements for instrumentation and monitoring works to be carry out by the Project Proponent for development and building works in MRT Railway Protection Zone (RPZ) in accordance with Railways (Railway Protection Zone) Regulations 1998.

PROFESSIONAL ENGINEER / ARCHITECT ENDORSEMENT FORM
Submission for works within MRT Railway Protection Zone (RPZ) must be endorsed by qualified submitting person which includes architects and engineers.

For any inquiries, please contact Elia Emizar Ng Adimon at 03-20832000 or email to dbc.general@mymrt.com.my